Pinnacle at Liberty Bay Planned Residential Development and Preliminary Plat
Overview
Pinnacle at Liberty Bay is a proposed Subdivision and Planned Residential Development (PRD) located on approximately 42 acres in the Residential Low (RL) zone of Poulsbo. The site is situated between the existing Crystal View and Baywatch neighborhoods. Physical characteristics of the property include a mix of gentle to steep slopes, second- and third-growth forest consistent with historical logging activity, several wetlands, and three stream segments or drainages. The proposal includes 130 single-family residential lots, along with associated infrastructure such as internal roads, open space, stormwater management facilities, and preservation of critical areas and required buffers. Vehicular access is proposed via Johnson Parkway NE on the east. The development also proposes to complete a segment of Sunrise Ridge Avenue NE, connecting to the Johnson Parkway NE roundabout, which would establish a continuous east-west connection and improve access for public and emergency services in the area.
Quick Facts
General Project Summary
-
Project Name: Pinnacle at Liberty Bay
-
Location: Between Crystal View and Baywatch developments in Poulsbo, WA
-
Site Size: ~42 acres over 4 parcels
-
Zoning: Residential Low (RL)
-
Development Type: Preliminary Subdivision + Planned Residential Development (PRD)
- Mix of “daylight”, “tuck-under”, and “flat” lots with 1detached single-family homes
Open Space and Amenities
-
Tree Retention: 840 significant trees retained (exceeds 25% requirement). Tree Retention peer reviewed.
-
Open Space Tracts: Multiple tracts throughout the site providing passive and active space
-
Parks: Includes several small parks distributed across the three phases
-
Trails: Soft-surface trails connect open spaces and follow critical areas
Traffic and Access
-
Primary Access Points: Johnson Parkway NE (east), Completion of Sunrise Ridge Avenue NE (internal arterial connection)
-
Trip Generation: AM Peak: 114 trips, PM Peak: 151 trips
- TIA peer reviewed
Stormwater Facilities:
-
Multiple storm ponds located throughout the site
-
Designed per 2019 SWMMWW (Stormwater Manual for Western Washington)
- Stormwater Report peer reviewed
Critical Areas
-
Streams and Wetlands: Several on site (Streams A–D, Wetlands A–D)
- Habitat Management Plan peer reviewed
Project Documents
Please Note: The City will continue to accept public comments on the Pinnacle at Liberty Bay project until a final decision is issued. Additional opportunities to provide comment include the November 17, 2026 Planning Commission public meeting and the Hearing Examiner public hearing, tentatively scheduled for January 15, 2027.
Planning Commission Public Meeting - November 17, 2026
Note: Public Meeting cotninued to November 24, 2026 at 6pm. Additional info can be found here (when available).
November 17, 2026, Notice of Planning Commission Public Meeting, for the Pinnacle at Liberty Bay Planned Residential Development and Preliminary Subdivision.
- 1: Staff Report (dated November 6,2026)
- 2: Application Materials
- 2.a: Application Materials
- 2.b: Overall Site Plan and Phasing Plan (9/16/26)
- 2.c: Preliminary TESC (9/16/26)
- 2.d: Preliminary Grading Plans (9/16/26)
- 2.e: Overall Infrastructure Plan (9/16/26)
- 2.f: Preliminary Road and Utility Plan (9/16/26)
- 2.g: Preliminary Road and Utility Profiles (9/16/26)
- 2.h: Preliminary Pond Layout and Profiles (9/16/26)
- 2.i: Off-Site Sewer Connection/Crossing Plan (9/16/26)
- 2.j: Channelization and Signage Plan (9/16/26)
- 3: Landscape and Recreation Plan
- 4: Individual Identity Plan, Home Designs, and Narrative
- 5: Critical Areas
- 5.a SWC Pinnacle at Liberty Bay Critical Area Report and Habitat Management Plan (7/14/25)
- 5.b: Farallon/Grette Associates Peer Review (8/29/25)
- 5.c: SWC Critical Area Report Addendum (11/19/25)
- 5.d: Farallon/Grette Associates Peer Review (12/4/25)
- 5.e: SWC Critical Area Report Addendum No. 2 (4/6/26)
- 5.f: Farallon/Grette Associates Peer Review (4/27/26)
- 5.g: SWC Critical Area Report Addendum No. 3 (9/15/26)
- 5.h: Farallon/Grette Associates Peer Review No. 4 (10/14/26)
- 5.i: Wetland Buffer Averaging Civil Sheet (9/16/26)
- 6: Geotechnical
- 6.a: Aspect Geotechnical Engineering Report (2/13/25)
- 6.b: Aspect Addendum (6/16/25)
- 6.c: HWA/GeoSciences Peer Review (10/3/25)
- 6.d: Aspect Response to City of Poulsbo’s Geotechnical Third-Party Review Comments (11/24/25)
- 6.e: Aspect Addendum N. 2 (6/17/26)
- 6.f: Aspect Geotechnical Addendum No. 3 (9/9/26)
- 7: Tree Retention Information
- 8: Stormwater
- 9: Traffic
- 9.a: Traffic Impact Analysis (Revised 10/26)
- 9.b: Traffic Impact Analysis (Revised 11/25)
- 9.c: Parametrix Peer Review (9/8/25)
- 9.d: Parametrix Peer Review No. 2 (7/1/26)
- 9.e: Parametrix Peer Review No. 3 (9/2/26)
- 9.f: Parametrix Peer Review (10/19/26)
- 9.g: Parametrix Connection Road Feasibility Independent Review (9/16/2026)
- 9.h: Concurrency Application
- 9.i: Applicant Response to City DRAFT Connectivity Memo (7/21/26)
- 9.j: Divoky Property Connection Feasibility Analysis
- 9.k: Skelley Property Connection Feasibility Analysis
- 9.l: Stream Crossing/Baywatch Connection Technical Justification
- 9.m: Access Separation Exhibit
- 9.n: Hinton Engineering Access Road Opinion
- 9.o: Poulsbo Fire District Operational Emergency Response Considerations memo (7/28/26)
- 9.p: City Building/Fire Code Official Access and Emergency Egress Review memo (8/19/26)
- 9.q: Engineering Memo – Connectivity and Multiple Points of Access/Egress (Bateman, Ranes 10/28/26)
- 9.r: Engineering Memo – Project Areas and Access Points ICC Code Interpretation (10/27/26)
- 9.s: WSDOT Review Memo (10/21/26)
- 10: Gray and Osborne Water System Analysis (11/14/25)
- 11. Original Notice of Application and Noticing Materials
- 12: Revised Notice of Optional w/Optional DNS Noticing Materials
- 13: Public Comment
- 13.a: Comments received during Notice of Application Comment Period 1
- 13.b: Comments received after Notice of Application Comment Period 1
- 13.c: Comment received during Notice of Application Optional DNS Comment Period 2
- 13.d: Comments received after Notice of Application and Optional DNS Comment Period 2
- 13.e: Summary Memo of Public Comment
- 14: Lockhart Administrative Determinations
- 15: Planning Commission Public Meeting Notice
November 17 Staff Presentation
Hearing Examiner Public Hearing - Tentatively Scheduled for January 15, 2027
Notice of Hearing Examiner Public Hearing for the Pinnacle at Liberty Bay Planned Residential Development and Preliminary Subdivision.
- 1: Staff Report (dated November 6,2026)
- 2: Application Materials
- 2.a: Application Materials
- 2.b: Overall Site Plan and Phasing Plan (9/16/26)
- 2.c: Preliminary TESC (9/16/26)
- 2.d: Preliminary Grading Plans (9/16/26)
- 2.e: Overall Infrastructure Plan (9/16/26)
- 2.f: Preliminary Road and Utility Plan (9/16/26)
- 2.g: Preliminary Road and Utility Profiles (9/16/26)
- 2.h: Preliminary Pond Layout and Profiles (9/16/26)
- 2.i: Off-Site Sewer Connection/Crossing Plan (9/16/26)
- 2.j: Channelization and Signage Plan (9/16/26)
- 3: Landscape and Recreation Plan
- 4: Individual Identity Plan, Home Designs, and Narrative
- 5: Critical Areas
- 5.a SWC Pinnacle at Liberty Bay Critical Area Report and Habitat Management Plan (7/14/25)
- 5.b: Farallon/Grette Associates Peer Review (8/29/25)
- 5.c: SWC Critical Area Report Addendum (11/19/25)
- 5.d: Farallon/Grette Associates Peer Review (12/4/25)
- 5.e: SWC Critical Area Report Addendum No. 2 (4/6/26)
- 5.f: Farallon/Grette Associates Peer Review (4/27/26)
- 5.g: SWC Critical Area Report Addendum No. 3 (9/15/26)
- 5.h: Farallon/Grette Associates Peer Review No. 4 (10/14/26)
- 5.i: Wetland Buffer Averaging Civil Sheet (9/16/26)
- 6: Geotechnical
- 6.a: Aspect Geotechnical Engineering Report (2/13/25)
- 6.b: Aspect Addendum (6/16/25)
- 6.c: HWA/GeoSciences Peer Review (10/3/25)
- 6.d: Aspect Response to City of Poulsbo’s Geotechnical Third-Party Review Comments (11/24/25)
- 6.e: Aspect Addendum N. 2 (6/17/26)
- 6.f: Aspect Geotechnical Addendum No. 3 (9/9/26)
- 7: Tree Retention Information
- 8: Stormwater
- 9: Traffic
- 9.a: Traffic Impact Analysis (Revised 10/26)
- 9.b: Traffic Impact Analysis (Revised 11/25)
- 9.c: Parametrix Peer Review (9/8/25)
- 9.d: Parametrix Peer Review No. 2 (7/1/26)
- 9.e: Parametrix Peer Review No. 3 (9/2/26)
- 9.f: Parametrix Peer Review (10/19/26)
- 9.g: Parametrix Connection Road Feasibility Independent Review (9/16/2026)
- 9.h: Concurrency Application
- 9.i: Applicant Response to City DRAFT Connectivity Memo (7/21/26)
- 9.j: Divoky Property Connection Feasibility Analysis
- 9.k: Skelley Property Connection Feasibility Analysis
- 9.l: Stream Crossing/Baywatch Connection Technical Justification
- 9.m: Access Separation Exhibit
- 9.n: Hinton Engineering Access Road Opinion
- 9.o: Poulsbo Fire District Operational Emergency Response Considerations memo (7/28/26)
- 9.p: City Building/Fire Code Official Access and Emergency Egress Review memo (8/19/26)
- 9.q: Engineering Memo – Connectivity and Multiple Points of Access/Egress (Bateman, Ranes 10/28/26)
- 9.r: Engineering Memo – Project Areas and Access Points ICC Code Interpretation (10/27/26)
- 9.s: WSDOT Review Memo (10/21/26)
- 10: Gray and Osborne Water System Analysis (11/14/25)
- 11. Original Notice of Application and Noticing Materials
- 12: Revised Notice of Optional w/Optional DNS Noticing Materials
- 13: Public Comment
- 13.a: Comments received during Notice of Application Comment Period 1
- 13.b: Comments received after Notice of Application Comment Period 1
- 13.c: Comment received during Notice of Application Optional DNS Comment Period 2
- 13.d: Comments received after Notice of Application and Optional DNS Comment Period 2
- 13.e: Summary Memo of Public Comment
- 14: Lockhart Administrative Determinations
- 15: Planning Commission Public Meeting Notice
Addendum to the Planning Commission Staff Report and Exhibits
- New Exhibit 16: Staff Report Addendum No.1
- New Exhibit 17: Planning Commission Findings of Fact, Conclusions, and Recommendation
- New Exhibit 18: Notice of Hearing Examiner Public Hearing
SEPA Determination - November 2, 2026
Public Notices
- Notice of Application (8/27/25-9/11/25)
- Public comment received during Notice of Application comment period (provided to applicant)
- Revised Notice of Application and Optional DNS (6/17/26-7/1/26)
- Notice of SEPA Determination – Issued 11/2/26
- Notice of Planning Commission Public Meeting– Scheduled for 11/17/26
- Notice of Hearing Examiner Public Hearing – Scheduled for 12/3/26
- Notice of Decision
September 17, 2026 - Application Resubmittal
- Technical Review 4 Response Letter
- Civil Plan Set
- Individual Identity Plan and Narrative
- Divoky Connection Feasibility Letter
- Skelley Connection Feasibility Letter
- Stream Crossing Technical Justification
- Hinton Engineering Access Road Opinion
- Critical Area Report Addendum
- Geotech Addendum
- SEPA Checklist
- Traffic Impact Analysis (resubmitted 10/5/26)
Technical Review No. 5
Technical Review No. 4
July 21, 2026 - Application Resubmittal
June 25, 2026 - Application Resubmittal
June 18, 2026 - Application Resubmittal
Technical Review No. 3
Technical Review No. 2
- Request for Revisions Technical Review No. 2 – Sent 12/31/25
- Revised Request for Revisions – sent 1/9/26
- 90-Day Extenstion Request
December 2, 2025 - Application Resubmittal
- Technical Review No. 1 Response Letter
- Public Comment Response Matrix
- Civil Plans
- Phasing Plan
- Landscape and Open Space Plan
- Individual Identiy Plan
- SEPA Checklist (not yet reviewed by staff)
- Traffic Impact Analysis
- Stormwater Report
- SWC Peer Review Addendum
- Geotech Report Peer Review Addendum
- Draft CC&Rs
April 13, 2026 - Application Resubmittal
Technical Review No. 1
- Counter Complete Letter – Sent 7/18/25
- Technically Complete Letter– Sent 8/14/25
- Request for Revisions Technical Review No. 1 – Sent 9/8/25
July 2025 - Application Submittal
- Preliminary Subdivision Application Form
- Planned Residential Development Application Form
- Critical Areas Review Application Form
- Cover Letter
- PRD Narrative
- General Site Plans
- Landscape and Open Space Plans
- Tree Retention Arborist Report
- Grading Plans
- Utility and Street Plans
- Stormwater Report
- Geotechnical Report West and East
- Buffer Mitigation Plan and Habitat Management Plan
- Traffic Impact Analysis and Concurrency Application
- SEPA Checklist (not yet reviewed by staff)
- Individual Identity Plan and Preliminary Elevations
Project Timeline
Consistent with PMC Title 19, Project Permit Application Procedures for a Type III Application – Note: This is Step 2 in a 6-Step Review Process for Subdivisions
| Pre-Application Conference 1 | November 5, 2024 |
| Pre-Application Conference 2 | April 10, 2025 |
| Neighborhood Meeting | April 21, 2025 |
| Application Submittal Counter Complete | July 28, 2025 |
| Technically Complete | August 14, 2025 |
| Notice of Application Issued (14-Day Comment Period) | Issued August 27, 2025 (comments due September 11, 2025) |
| Request for Revisions Provided to Application | September 8, 2025 |
| Application Resbumitted | December 2, 2025 |
| Request for Revisions Provided to Application | January 9, 2026 |
| Application Resbumitted | April 13, 2026 |
| Request for Revisions Provided to Application | June 5, 2026 |
| Revised Notice of Application and Optional DNS Issued (14-Day Comment Period) | June 17, 2026 |
| Application Resbumitted | June 18, 2026 |
| Request for Revisions Provided to Application | July 30, 2026 |
| Application Resbumitted | September 17, 2026 and October 5, 2026 |
| SEPA Determination Issued (no comment period) | November 2, 2026 |
| Notice of Planning Commission Public Meeting Issued | November 9, 2026 |
| Planning Commission Staff Report Issued | November 6, 2026 |
| Planning Commission Public Meeting | November 17 and 24, 2026 |
| Notice of Hearing Examiner Public Hearing Issued | TBD |
| Hearing Examiner Public Hearing | Tentatively Scheduled for January 15, 2027 |
| Hearing Examiner Decision | TBD |
| Request for Reconsideration | TBD |
| Notice of Decision Issued | TBD |
| Appeal Period | TBD |
Email Notification