Pinnacle at Liberty Bay Planned Residential Development and Preliminary Plat

 

Overview

Pinnacle at Liberty Bay is a proposed Subdivision and Planned Residential Development (PRD) located on approximately 42 acres in the Residential Low (RL) zone of Poulsbo. The site is situated between the existing Crystal View and Baywatch neighborhoods. Physical characteristics of the property include a mix of gentle to steep slopes, second- and third-growth forest consistent with historical logging activity, several wetlands, and three stream segments or drainages. The proposal includes 138 single-family residential lots, along with associated infrastructure such as internal roads, open space, stormwater management facilities, and preservation of critical areas and required buffers. Vehicular access is proposed via Johnson Parkway NE on the east. The development also proposes to complete a segment of Sunrise Ridge Avenue NE, connecting to the Johnson Parkway NE roundabout, which would establish a continuous east-west connection and improve access for public and emergency services in the area.

Quick Facts

General Project Summary

  • Project Name: Pinnacle at Liberty Bay

  • Location: Between Crystal View and Baywatch developments in Poulsbo, WA

  • Site Size: ~42 acres over 4 parcels

  • Zoning: Residential Low (RL)

  • Development Type: Preliminary Subdivision + Planned Residential Development (PRD)

  • Mix of “daylight”, “tuck-under”, and “flat” lots with 1detached single-family homes

Open Space and Amenities

  • Tree Retention: 840 significant trees retained (exceeds 25% requirement). Tree Retention peer reviewed.

  • Open Space Tracts: Multiple tracts throughout the site providing passive and active space

  • Parks: Includes several small parks distributed across the three phases

  • Trails: Soft-surface trails connect open spaces and follow critical areas

Traffic and Access

  • Primary Access Points: Johnson Parkway NE (east), Completion of Sunrise Ridge Avenue NE (internal arterial connection)

  • Trip Generation: AM Peak: 114 trips, PM Peak: 151 trips

  • TIA peer reviewed

Stormwater Facilities:

  • Multiple storm ponds located throughout the site

  • Designed per 2019 SWMMWW (Stormwater Manual for Western Washington)

  • Stormwater Report peer reviewed

Critical Areas 

  • Streams and Wetlands: Several on site (Streams A–D, Wetlands A–D)

  • Habitat Management Plan peer reviewed

Project Documents

Technical Review No. 5
Technical Review No. 4
Public Notices
Staff Report

The July 7, 2026, Planning Commission Public Meeting for the Pinnacle at Liberty Bay Planned Residential Development and Preliminary Subdivision has been postponed.

Following review of the applicant’s most recent resubmittal materials from June 25th, City staff determined that additional technical revisions are necessary before the application can proceed. The requested revisions include roadway design information necessary to demonstrate compliance with the City’s adopted engineering and construction standards and to allow completion of the City’s technical review.

Once the requested information has been submitted and reviewed, the application will be rescheduled for a future Planning Commission Public Meeting. At this time, the City anticipates presenting the application to the Planning Commission on August 11, 2026, although that date remains subject to change based on the completeness of the applicant’s resubmittal and the City’s review.

Updated meeting information and public notice will be provided in accordance with the City’s standard noticing procedures.

June 25, 2026 - Application Resubmittal

Project Timeline

Consistent with PMC Title 19, Project Permit Application Procedures for a Type III Application – Note: This is Step 2 in a 6-Step Review Process for Subdivisions

Pre-Application Conference 1 November 5, 2024
Pre-Application Conference 2 April 10, 2025
Neighborhood Meeting April 21, 2025
Application Submittal Counter Complete July 28, 2025
Technically Complete August 14, 2025
Notice of Application Issued (14-Day Comment Period) Issued August 27, 2025 (comments due September 11, 2025)
Request for Revisions Provided to Application September 8, 2025
Application Resbumitted December 2, 2025
Request for Revisions Provided to Application January 9, 2026
Application Resbumitted April 13, 2026
Request for Revisions Provided to Application June 5, 2026
Revised Notice of Application and Optional DNS Issued (14-Day Comment Period) June 17, 2026
Application Resbumitted June 18, 2026
Notice of Planning Commission Public Meeting Issued TBD
Planning Commission Staff Report Issued TBD
SEPA Determination Issued (14-Day Comment Period) TBD
Planning Commission Public Meeting TBD
Notice of Hearing Examiner Public Hearing Issued TBD
Notice of Hearing Staff Report Issued TBD
Hearing Examiner Public Hearing TBD
Hearing Examiner Decision TBD
Request for Reconsideration TBD
Notice of Decision Issued TBD
Appeal Period TBD

* Additional technical review cycle may be required. TBD. 